Build Status – with an eye towards helping the community in their long-term recovery.

Roof Completed 9/7/24

Metal Roof Nearing Completion – 7/30/24

AC Installation on-going 7/29/24

2nd Floor Lanai – Will Raise Railing/Pony Walls to 42″ (Top 2×4 above) – 7/29/24

Stairs with a view (as planned) and cove lighting framed

Siding Mockup wins approval – 7/26/24

Pool Cover Closing Switch Conduit In Place

Pool Underground Plumbing Passes Inspection (Tested @35psi) – 7/25/24

Pool/Pond w/plumbing, electrical, and rebar almost ready for gunite – 7/24/24

Arriving for on-site visit – 7/24/24

Concept Design Etched Glass Master Bedroom Entry – 7/19/24

Metal Roof Installation Continues – 7/17/24

All exterior doors (minus front door) installed – 6/26/24

Window/Slider Installation Nearly Complete – 6/21/24

First Floor Sliders Installed (Minus Great Room Area) – 6/14/24

North Side Windows for Sabrina’s Room, Garage, 2nd Laundry Installed – 6/14/24

Arche-Duct Drains for Back Sliders for Mom’s/Sabrinas Rooms Installed – 6/6/24

Additional Front Windows Installed – 6/6/24

First Windows Installed in Mom’s Bedroom and Bathroom – 6/4/24

Tyvek installation completed for First Floor Walls – 6/3/24

All windows moved from Front to Inside House – 5/31/24

Lower Roof Sections Completed on South Front and Main Back – 5/27/24

Wooden Floor Completed At Factory – 5/25/24

Lower Standing Seam Sections Completed over Garage Area – 5/24/24

First Marine Green Roof Sections Installed on 2nd Floor Roof – 5/16/24

Standing Seam Rolls Arrived, and Shaped into Roofing Sections Needed – 5/16/24

Windows/Doors/Sliders Arrive and Are Stacked In Front of House – 5/16/24

Marine Green Metal Valley Underlays All In Place – 5/2/24

First Marine Green Roof Material Arrives and Starts Being Installed – 4/29/24

Based on mockups, decided to go with pony walls on 2nd Floor Lanai – 4/29/24

2nd Floor Lanai Pony Wall vs Half Wall Mockups – 4/29/24

Initial On-Site Painting Trials By Tamara and Dwight – 4/28/24

Full set of Trusses in Place – 1/5/24

2nd Floor Roof Trusses Start Rising – 1/3/24

Great Room Peak Trusswork Completed – 1/2/24

Last Sunset of 2023

Christmas Morning 2023

Main Truss work complete for 1st Floor – 12/19/23

Truss work continues for Garage Side – 12/18/23

Main Trusses in Place for Mom’s Suite and Great Room – 12/15/23

First Roof Trusses Put in Place – 12/14/23

2nd Floor Wall Plywood Starts To Be Applied – 12/13/24

Roof Trusses Arrive 12/12/23

Ariel Views 11/10/23

Initial Framing through Thanksgiving Day 2023
Full Build Progression though Thanksgiving Day 2023

Ready for Framing – 10/12/24

The Pour: 10-11-23

June 1, 2023 : Building Permits issued

Day 1 – May 15th, 2023

Land Blessing – 4/29/23